#ETJBPCOIELECTRIFICATIONUPDATES
#PPIJBPEFICATIONUPDATES
#jbpnews
Fir wahi hua jo itne saalo se hota aa rha hai ET-ALD(Coi) electrification project k sath or firse Majhgava-STA-Rewa ka electrification hone ka target March 2019 ho gaya hai so ab JBP-ALD section me elocos 2019 k pehle chalna mushkil hai magar khushi ki baat ye hai ki PPI-JBP section ka kaam Nov 2017 me pura krne ka...
more... target hai jo pura bhi ho jayga or shankargarh-MKP ka kaam pura krne ka target OCT 2017 hai so ye do sections ye saal hi complete ho sakte hai magar baaki bache sections 2018 or 2019 me hi pura ho paynge
Sections status/target
ET-PPI electrification work- Completed
PPI-JBP electrification work- Nov 2017
JBP-KTE electrification work- March 2018
KTE-STA electrification work- Dec 2018
Majhgava-STA-Rewa electrification work- Mar 2019
MKP-Majhgava electrification work- Dec 2018