Connecting Uttarakhand: Progress Report of Rishikesh - Karnaprayag Project :
1) Overall Progress: 33%
2) Tunnelling Work: 83 km Completed.
3) Breakthrough of two drives of the Main & Escape tunnels: Completed.
4)...
more... 2 important Rail bridges & 3 Road bridges: Completed.
please wait...Translate to HindiConnecting Uttarakhand: Rishikesh - Karnaprayag Project ki Progress Report:
1) Overall Progress: 33%
2) Tunnelling Work: 83 km Pura Hua.
3) Main aur Escape Tunnels ke do drives ka breakthrough: Pura Hua.
4) 2 important Rail bridges aur 3 Road bridges: Pura Hua.