Delhi-Varanasi-Kolkata HSR Status
Delhi-Varanasi Route: -
LİDAR survey commenced January 2021 from Greater Noida
- Detailed Project Report (DPR) underway
- Land acquisition will start once all state governments approve...
more... the DPR
Varanasi-Patna-Kolkata Route: -
Growever Infra emerged as the lowest bidder to prepare the final alignment design through an aerial LiDAR survey for the Detailed Project Report (DPR) on March 2021
- Stations might come up at Buxar, Arrah, Patna, Bihar Sharif - Nawada, Dhanbad, Asansol, Durgapur, Bardhaman and Howrah
- Land acquisition will start once all state governments approve the DPR (+)