DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 93% done including cross bars at railway stations (Completion expected by Aug2019)
Brackets - 07% done (Completion expected by Oct2019)
Wiring - Yet to start (Completion expected by Dec2019)
SSP...
more... - Foundation at SD and STP completed (Completion expected by Dec2019)
OHE wire energized - Expected by end of Jan2020
CRS inspection - Expected by Feb2020
Commercial uses - Mar2020
** All provided dates are tentative.