The flood damaged portion of track on the UP line along with bridge no 133 between Sudhani and Telta station has been certified fit by the Engineering department of N.F.Railway at 13-25 p.m. today. The first goods train which left Sudhani station at 13-50 p.m. to arrive Telta at 14-25 p.m. passed over that section safely. The portion has been certified fit upto a maximum speed of Stop dead 10 KMPH.
The portion of repaired track will be kept under very close observation under the passage...
more... of goods trains and movements of passenger trains will be commenced from 3rd September. With the movements of goods trains, the flow of incoming essential commodities to the Northeast area will be restored. The speed restriction will continue and all trains in the effected section will ply at restricted speed till such time that permanent repairs are carried out. It is to be mentioned that very extensive damage has been caused in the vicinity of bridge no 133 with scouring to a depth of 12 to 15 meter and extent of 70 meter in the approach of the bridge.
It may be mentioned here that train services over parts of Bihar and West Bengal under Katihar and Alipurduar Divisions of N.F. Railway had to be suspended due large scale damage of track in many locations. Thereby disrupting direct train communication of NE Region with rest of the country.
Estimated commercial loss from 13th to 28th August, 2017:
Nos of Mail/Express trains cancelled : 821 nos
Nos of passenger trains cancelled : 484 nos
Total loss in PRS : Rs. 47.53 crs
Total loss in Non-PRS : Rs. 5.30 crs
Ticket checking segment : Rs. 1.44 crs
Passenger reduced (PRS) : Rs. 4,02,653 nos
Passenger reduced (Non-PRS) : Rs. 11,27,277 nos
Loss from Goods booking : Rs. 16.26 crs
Loss from Parcel booking : Rs. 3.51 crs.
Total Commercial loss amounts to Rs. 74.04 crs. This is apart from the amount which has been refunded to passenger. The losses to other departments like Engineering, Signal & Telecommunication etc. are being assessed.
Thousands of labors along with railway officials worked round the clock at all damaged sites to restore the train services during this period.