WR Railway Project - #Ratlam #Indore #Mhow Sanawad GC Target
(Rau - Mhow) DL 9.51 Km - Dec 23 (work in progress).
(Mhow- Patalpani) 5.51 km -...
more... Dec 23 (work in progress, mg track removed).
(#Sanawad -
#Omakareshwar) 5.40 km - Jan 24 (work in progress, mg track removeing now).
(Muktiyara - Omakareshwar) 20.7 Km - Oct 24 (work in progress, narmada river bridge work in under construction).
(#Patalpani- Muktiyara) 64.97 Km - Mar 26 - FLS Survey Done by
#RITES. Forest Land Proposal sent. 4 km tunnel tender is under process.
Forest Land Proposal : FP/MP/RAIL/427846/2023
Clearance Type: Form-A (Part-I): Diversion of Forest Land
CAF No. : CAF/124916/2023
S/W No.: SW/127736/2023
Dr. Ambedkar Nagar (Exculding yard) to muktiyara balwara (Exculding yard) for Existing/new detour BG line in connection with Gauge conversion of existing Ratlam
#Khandwa MG section of western Railway
Area: 289.015 ha
Category : Railway
Date of Submission: 07/06/2023
Pending at UA due to EDS by MS after PSC-I
Regards,
Mohit Saxena
SonOfGalaxy
please wait...Translate to EnglishWR Railway Project - Yo, check out this dope info about the Ratlam, Indore, Mhow, and Sanawad GC targets.
(Rau - Mhow) DL 9.51 Km - Dec 23 (still work in progress, ya know).
(Mhow- Patalpani) 5.51 km - Dec 23 (still work in progress, mg track removed, damn).
(#Sanawad - #Omakareshwar) 5.40 km - Jan 24 (still work in progress, mg track being removed as we speak).
(Muktiyara - Omakareshwar) 20.7 Km - Oct 24 (still work in progress, the narmada river bridge work is under construction, fam).
(#Patalpani- Muktiyara) 64.97 Km - Mar 26 - FLS Survey Done by #RITES. Forest Land Proposal sent. 4 km tunnel tender is under process (woo hoo).
Forest Land Proposal : FP/MP/RAIL/427846/2023
Clearance Type: Form-A (Part-I): Diversion of Forest Land
CAF No. : CAF/124916/2023
S/W No.: SW/127736/2023
Dr. Ambedkar Nagar (Excluding yard) to muktiyara balwara (Excluding yard) for Existing/new ...
please wait...Translate to HindiWR Railway Project -
#Ratlam #Indore #Mhow Sanawad GC Target
(Rau - Mhow) DL 9.51 Km - Dec 23 (work in progress).
(Mhow- Patalpani) 5.51 km - Dec 23 (work in progress, mg track removed).
(#Sanawad -
#Omakareshwar) 5.40 km - Jan 24 (work in progress, mg track removeing now).
(Muktiyara - Omakareshwar) 20.7 Km - Oct 24 (work in progress, narmada river bridge work in under construction).
(#Patalpani- Muktiyara) 64.97 Km - Mar 26 - FLS Survey Done by
#RITES. Forest Land Proposal sent. 4 km tunnel tender is under process.
Forest Land Proposal : FP/MP/RAIL/427846/2023
Clearance Type: Form-A (Part-I): Diversion of Forest Land
CAF No. : CAF/124916/2023
S/W No.: SW/127736/2023
Dr. Ambedkar Nagar (Exculding yard) to muktiyara balwara (Exculding yard) for Existing/new detour BG line in connection with Gauge conversion of existing Ratlam
#Khandwa MG section of western Railway
Area: 289.015 ha
Category : Railway
Date of Submission: 07/06/2023
Pending at UA due to EDS by MS after PSC-I
Regards,
Mohit Saxena
SonOfGalaxy